A traceability matrix becomes useful when a reviewer can follow a requirement all the way to the evidence supporting a release decision. A row marked “passed” tells only part of the story. The reviewer also needs the requirement revision, the configuration under test and the result that justifies the disposition.
Start with a row you can verify
Consider a fictional packaging machine. Requirement REQ-104, revision 2, states that if the label reader reports no readable code, the controller shall route the package to the reject lane before the next package reaches the diverter. It applies to the Model B configuration.
Record REQ-104 revision 2, Model B, the verification method and the linked procedure TEST-031 revision 4. The procedure runs with an unreadable label under the stated operating conditions. Link the execution record, which identifies the controller build, equipment configuration, date and observed results. If the procedure fails, link the defect and record the disposition. Keep failed records available when a subsequent execution passes.
Choose columns that support decisions
Capture the requirement ID and revision, source or parent requirement, applicable product variant or baseline, verification method, procedure ID and revision, execution record, result, linked defect or exception, and a responsible owner. Include acceptance criteria in the linked requirement or procedure so a reviewer can see how the outcome was judged.
Track coverage and execution separately. A requirement can have a test procedure linked and still be awaiting execution. Use practical statuses such as missing verification method, planned, executed and passed, failed, or under review following a change. Record why any verification is deferred and where the disposition was approved.
Recheck evidence after a requirement changes
Suppose revision 3 tightens the timing condition. Follow the existing link to TEST-031, review whether the procedure measures the new condition, and decide which configurations need another run. Keep the earlier passing result associated with revision 2. If the earlier evidence also supports revision 3, record the reasoning and approval so it can be reviewed later.
Before an engineering review, pick a sample of changed requirements and trace forward to execution records. Then sample recent test executions and trace back to the requirements they cover. This catches both unsupported requirements and tests whose purpose has become unclear.
The same fields work in a spreadsheet or a lifecycle tool. The discipline is to keep authoritative records where they are owned and make the links usable from the review. See requirements baselines and change management and getting started with IBM DOORS Next.